Procurement
How a buyer decides
- Is black start or islanded operation in scope? Then it is decided: a grid-following
converter cannot energize a dead network or hold an island alone. Black start is the one binary here, and it must be specified and tested, never inferred.
- Otherwise start at the connection point. Short-circuit ratio is fault MVA at
the node over the plant's own MW rating, so resizing changes it — double the rating and you
halve the ratio. Get it for your point of interconnection from the operator, and ask which definition.
- Read the code before the datasheet: most write duties both modes must meet,
and a few write the mode into the requirement.
That is enough to decide. Code names the mode, or the ratio is at or below the vendor's
stated minimum: grid-forming, with the project-specific stability study budgeted. Code
silent and the ratio still clear of that minimum in the weakest credible case — after the
outage that thins the network, and with the neighbouring converters counted against you
rather than ignored — grid-following. Chile writes that second test into law for a
grid-following plant, which must verify a short-circuit ratio of at least 3 and an
equivalent ratio, counting neighbouring converters against you, of at least 1.5. Between the
two it is a study question before a mode question: the weak-grid one. Which model class answers it, and what the answer has to say, is not a detail. A service you intend to sell that prices the capability overrides the
ratio.
Then the question that outlives it. Grid-forming is often — not always — the same hardware
running different control software; Chile assumes as much, limiting an instructed mode
change to software and communications. So ask each bidder whether the unit is grid-forming
capable or field-upgradeable, what it costs, what headroom backs the rated response at your
ratio, and what type test and model delivery stand behind the answer: a capability answer is
worth what its evidence is, and the grid-forming and grid-following entries carry what to demand. A plant studied in one mode must be re-studied for the other.
Whether that headroom must be bought as oversizing belongs to the code and the contract, and
the three are not answering about one quantity. Chile makes at least 1.3 pu of rated
current for 5 seconds a design requirement, with reactive and active overcurrent
margins held against it. Finland and Switzerland say only that the storage capacity need not be
overdimensioned for grid-forming control — a different quantity, and no waiver of the current
headroom. A reserved state-of-charge band is a market-and-contract matter too, and belongs in
the capacity warranty.