The BESS sizing calculator. The waterfall, interactive.

Enter a contract — power, duration, guarantee year — and watch it walk backward through every real-world loss to the DC nameplate you'd actually have to buy. The same method as the sizing guide, with your numbers — and the same math behind our computed analysis of the BOL overbuild.

Assumptions

Contract
Loss chain · POI → cell
Warranty & power side

The energy waterfall

Contract: 400 MWh usable at the POI (100 MW × 4 h)

  1. HV transformer (POI is on the HV side)402 MWh

    The offtake meter sits on the HV side, so the step-up transformer is the first loss you buy back — 99.5% on the discharge leg.

  2. AC cabling403.2 MWh

    MV/HV AC runs and terminations between the transformers.

  3. Auxiliary / ancillary loads411.4 MWh

    Thermal management, controls, and standby draw ~2% of throughput — a serious model books this as its own line, not a footnote.

  4. MV transformer415.6 MWh

    The medium-voltage step-up between the PCS and the collection bus.

  5. PCS conversion421.9 MWh

    The inverter's own conversion loss on the discharge leg.

  6. DC cabling423.2 MWh

    Cable runs and fusing from the racks to the PCS.

  7. Usable SoC window (DoD)427.5 MWh

    The BMS reserves headroom at the ends of the SoC range; only 99% of installed energy is dispatchable.

  8. Production-to-BOL cell fade429.6 MWh

    Cells lose a little capacity between the factory and first commissioning.

  9. Cell one-way efficiency442.9 MWh

    The cell's own round-trip loss, counted on the discharge half.

  10. Degradation to year 20 (SOH 70%)632.7 MWh

    Size so the fleet still clears the contract in year 20, once it has faded to 70% of BOL — unless you augment mid-life instead of overbuilding on day one.

632.7 MWhDC nameplate to install (1.58× contracted) — sized so it still delivers in year 20
442.9 MWhif you only sized for day one (1.11× — the loss chain alone, no degradation)
0.16 Cdischarge C-rate against the installed pack
105.3 MVA → 30 × 3.6 MVAPCS fleet: converters are sized in MVA, not MW — at PF 0.95, 100 MW needs 105.3 MVA (108 MVA installed)
The guarantee-point sentence

400 MWh usable at the POI, deliverable at 100 MW, in year 20, after the full HV-transformer-to-cell loss chain, a 99% SoC window, and 70% SOH.

First-pass educational estimate. Real projects add temperature/altitude derating, cycling-dependent degradation curves, augmentation strategies, and vendor-specific capability data — exactly what the sizing guide, the overbuild analysis, and the full course teach.

Use it in your work

Link or cite this tool

Free to use and link. Citation: BESS Sizing Calculator, BESS.courses — https://bess.courses/tools/bess-sizing/