The augmentation planner. A contract crossing a curve.

Every BESS contract is a floor; every battery is a curve descending toward it. This planner models the whole fleet vintage by vintage — each block ageing from its own install year — and answers the question guides rarely compute: by when must you order, and how many blocks per event. Companion to the augmentation definition and the sizing calculator.

Skip to the planner ↓

Two ways to add

AC or DC: what you are actually buying

Settle this before the arithmetic. The planner below tells you how much and by when; this tells you how the new blocks connect — and the two routes buy different things: one adds energy and power, the other adds energy alone. The drawing shows both over the same plant, so what each route costs in equipment is a downward glance rather than a memory test.

The same plant, augmented two ways. Above: AC augmentation adds a second complete energy station — battery, PCS and MV transformer — onto the MV collection bus, raising energy and power. Below: DC augmentation lands new blocks behind the existing PCS through per-string DC/DC converters, raising energy only. Battery existing blocks PCS DC ⇌ AC MV transformer MV collection bus POI / grid metering point New battery own DC bus New PCS adds MW New MV transformer Battery existing blocks PCS DC ⇌ AC MV transformer MV collection bus POI / grid metering point New battery DC-coupled DC/DC per string
Typical single-line arrangements, illustrative — real plants vary. The upper and lower halves are the same plant with the same components in the same columns; only the addition, in copper, differs. Hover or focus any component for what it is and why it is there; on a phone, scroll the drawing sideways.

AC augmentation — energy and power

  • Benefit: Adds energy and power — the second station raises both.
  • Benefit: Fully decoupled: its own DC bus and PCS, so no vintage-mixing constraints against the aged fleet.
  • Benefit: Vendor-open — the new station does not have to match the incumbent's DC ecosystem.
  • Drawback: The most equipment per event: battery, PCS, transformer and switchgear — plus the pad space and MV bay they occupy, reserved on day one.
  • Drawback: The added MW only earns inside the interconnection limit — power above the contracted export cap needs the study and the agreement reopened.
  • Drawback: Raises the aggregate short-circuit current at the POI — see below.

DC augmentation — energy only

  • Benefit: The least equipment per added MWh: blocks plus DC/DC converters — no new PCS, transformer or MV bay.
  • Benefit: Lands behind the existing interconnection — energy only, so no new export capacity to study. The new containers still need plot space and separation.
  • Benefit: The DC/DC converter isolates the new cells' voltage and state of charge from the aged racks.
  • Drawback: Energy only — the existing PCS still caps peak power, and at a fixed duration the extra energy can strand.
  • Drawback: Spends the headroom of the existing PCS, transformer and DC-side provision — headroom that was decided at the original design.
  • Drawback: Deepens the tie to the incumbent vendor's DC ecosystem and warranty interfaces.
The arithmetic

How much, and by when

Measure at
Strategy

MEASURE AT is the plane where your contract counts the MWh — pick the one it names, because the same fleet reads a different size at each. "BOL only" sizes the fleet for day one so you can watch the floor cross; the other presets solve the year-end sizing — staged plans still show the structural pre-event gap. Edit any block count by hand to override the solver — "Re-solve" hands sizing back to it.

Assumptions

Degradation preset

Illustrative — typical shape, not a warranty. Use your supplier’s warranted curve for any commercial decision.

Contract
Blocks
Money — your numbers, not ours
Schedule
Initial build
Pass, with 2 gapsmin buffer 0.1 MWh at HV, checked at each year end — but the fleet dips below the floor after yr 9.0 until the year-10 blocks land, and after yr 14.0 until the year-15 blocks land. See the decision schedule.
201blocks over the horizon (173 at COD)
$102.6MNPV capex at 6.0% ($110.6M undiscounted)
Yr 8.0order for the year-10 event — floor crossed yr 9.0
0237475712949yr 0yr 5yr 10yr 15yr 20contract floorcrosses (no yr-10 event)decide by+13+15Illustrative — typical shape, not a warranty. Use your supplier’s warranted curve for any commercial decision.
  • Initial fleet (173 blocks)
  • +13 blocks, yr 10 (cumulative)
  • +15 blocks, yr 15 (cumulative)
  • Contract floor (640 MWh at HV)

The decision schedule

  • Without the year-10 event the fleet crosses the floor at year 9.0. At 12 months lead, that order is placed by year 8.0.
  • Without the year-15 event the fleet crosses the floor at year 14.0. At 12 months lead, that order is placed by year 13.0.
  • The pre-event gaps are structural to a plan solved at year-end checks: blocks bought for an event add nothing before it, so the fleet sags below the floor for the months before each event. If your contract's capacity tests fall inside such a window, cover it with a few extra initial blocks or an earlier event — the year-end sizing itself is the reference model's convention, kept deliberately.
How to read the result

Three ways the answer misleads

The measurement plane

The same fleet reads five different sizes depending on where you measure it — nameplate, DC bus, PCS terminals, MV or HV. The contract names one plane; size against any other and the error compounds silently. At the defaults, a block's nameplate-to-HV ratio is about 0.91 on day one, before any degradation — 0.94 from the seven editable loss factors (BOL SOH contributes nothing at its 100% default), the rest from the preset's efficiency curve.

Warranted vs real curve

The presets are illustrative shapes, not warranties. Your supplier's warranted curve — with its cycling assumptions and its remedies — is the only curve a commercial decision should stand on. Paste-your-own-curve is the planned upgrade.

Granularity rounding

Blocks are bought whole, and each event is sized against the new block's deliverable energy in the worst year of the window it must cover — from its own year to the next event's — not its nameplate. At the defaults that is the difference between 11 blocks that fail the contract and 13 that hold it. The mirror of that rounding is stranding: energy a fixed PCS rating cannot move within the rated duration, reported under “Show the loss chain & stranding check”.

The money

Overbuild, stage, or blend — who pays for the fade, and when

Front-loading buys cells that sit underused for years and spends capital early; back-loading defers spend but exposes the project to future cell prices, integration labour, and the near-certainty that the original cell SKU is discontinued — formats and chemistries turn over every few years, so a year-10 top-up almost never uses the original part. The historical case for deferral is the price of the thing being deferred: lithium pack prices fell roughly 90% from 2010 to 2025, from around $1,200/kWh to about $108/kWh (BNEF), and the time value of money argues on the same side.

But the bet is symmetrical — deferral converts a known year-0 price into a forecast of a price nobody controls, and that forecast is yours to make: the planner takes your block cost and your discount rate and publishes no price forecast of its own. Lenders' independent engineers scrutinise the augmentation reserve directly, because the capacity warranty and the revenue contract both depend on the plan holding.

Timing is not only financial. At constant MW output the real C-rate rises as capacity fades — a fleet built at 0.25C runs near 0.3C once retention reaches about 80% — and both the BMS current limits and the warranty degradation model must budget for that creep unless new capacity relieves it. Adding capacity relieves per-cell duty — lower depth of discharge and C-rate spread over more installed energy — which slows the cycling contribution to fade; it does nothing for calendar ageing, which arrives on schedule regardless. The alternative is concrete: periodic capacity tests come in below the guaranteed table, and the shortfall lands as liquidated damages.

Three working defaults

These bands are practitioner judgement — the author's operating rule of thumb from real projects, not an industry statistic. Nobody publishes a number here; treat them as a starting position to beat with your own curve and prices.

  • Most cost-effective, lowest availability: ~0–5% overbuild at commercial operation (COD) with roughly annual augmentation — the least idle capital, and the most outages, orders and retests.
  • Most expensive, highest availability: ~30–40% oversize on day one — the floor is cleared by construction for years, at the price of cells that idle.
  • Balanced: ~10% overbuild, first augmentation around year 3–5, then roughly every five years — the shape most real projects converge on.
The decision, aspect by aspect

Oversize day one vs frequent augmentation

Aspect Oversize on day one Staged augmentation
Capex profile All capital at COD; surplus cells idle for years. Deferred spend, each event priced at its own year's market — cheaper only if $/kWh keeps falling, an assumption you own, not a forecast we make.
Performance risk Lowest — the floor is cleared by construction deep into the term. Concentrated at each event: a late order, a slipped outage or a hotter-than-warranted duty eats the margin. The decide-by date above is this row's mitigation.
Permitting & compliance One permit, one safety case, one interconnection study. Each event meets the code edition and study rules in force at its date — NFPA 855 and the interconnection rules at year 8 may be stricter than the ones the plant was permitted under.
Operational impact No augmentation events after COD — the surplus fleet still takes ordinary O&M. Outage windows, isolation, retest and model re-baselining at every event.
Technology trajectory Locked into today's cells at today's density for the whole term. Each event buys the current generation — and almost never the original SKU, so integration is engineering, not shopping.
Finance & tax timing Larger day-one basis; in some jurisdictions investment incentives attach to the installed nameplate — jurisdiction-specific and time-limited, so check the mechanism with your adviser rather than assuming it. Smaller basis spread over the term; the augmentation reserve is a named line lenders' engineers test.
Day one decides year eight

What you must reserve before the first block fades

A staged plan is only cheap if the addition is an installation, not a construction project inside an energised plant. That is decided at the original design: reserved land with foundations, trenching and conduit run; spare MV feeder positions; PCS and transformer headroom for the future blocks; a DC voltage window the year-8 market can still match; and priced module options in the supply agreement. Augmentation space left as bare land tends to be value-engineered away or quietly repurposed — a deferral plan with no reserved plot, no conversion headroom and no answer on cell availability is not a strategy; it is an assumption that year-8 engineering will be free.

Old cells, new cells

Mixing vintages is an engineering problem, not a spreadsheet line

A series string is limited by its weakest module, and racks paralleled on a shared DC bus are forced to the weakest string's operating window — so adding fresh, high-state-of-health (SOH) strings alongside aged ones creates a mismatched fleet the BMS and EMS must manage. DC-coupled designs handle it with per-string DC/DC conversion (the copper box in the diagram above), and vendors typically require augmentation racks on a separate DC bus or a dedicated PCS input. Every addition must also respect the as-built design — above all the DC voltage window (typically up to 1500 VDC) and the safety case: container footprint and separation under NFPA 855, and the site's explosion-protection basis, where UL 9540A test data informs NFPA 68/69 measures. New containers generally must match — or formally re-open — the commissioned safety case with the authority having jurisdiction (AHJ), under whatever code edition is in force at the time of the addition.

Five documents

Where the obligation actually lives

You meet augmentation across five documents. The battery supply agreement carries the capacity warranty and its warranted degradation curve, with operating-envelope conditions — cycles per year, depth of discharge, temperature, C-rate, resting SOC — that void coverage if breached. A capacity-maintenance or long-term service agreement commits the integrator to keep deliverable energy on that curve, augmenting at its own cost or at pre-agreed unit prices. The tolling or capacity contract defines the tested energy at the POI and the liquidated damages for shortfall, while availability guarantees cap how much outage time an augmentation installation may consume. The interconnection study, finally, fixes whether new blocks even fit the approved plant.

Working a project, ask five questions:

  1. Where is guaranteed energy measured — DC, PCS terminals, or net at the POI — and does the vendor state the degradation curve at that plane?
  2. Who bears future cell-price and technology risk? Fixed-price augmentation options are valuable and rare — ask how capacity is priced per rack, how long the option holds, and what happens if the vendor substitutes a different cell mid-life.
  3. What physical provisions are actually built on day one?
  4. How does the warranty treat a blended fleet — does the supplier restart the degradation clock only for newly added equipment, leaving the aged fleet on its original curve?
  5. Does the interconnection agreement already permit the addition, or does it trigger a fresh study cycle?
Event day

Executing an event, and re-baselining after it

An augmentation event is an outage with paperwork on both sides. Before it: the order placed by the decide-by date, the outage window agreed inside what the availability guarantee allows, and the safety case confirmed with the AHJ. During it: isolation, installation, and the commissioning capacity test that resets the contractual baseline. After it: the degradation model is re-baselined, because the schedule is steered by rack-level state-of-health telemetry against periodic capacity tests — not by the financial-close spreadsheet. Fade curves are warranted only under a specified duty; if the market pulls the plant into heavier cycling, real fade outruns the curve, and extrapolating early state-of-health data linearly to year 20 flatters the budget from the other side, because degradation has a late-life knee. Re-forecast at each capacity test and each major regulatory change.

In order of irreversibility

The checklist, ordered by when each item stops being reversible

  1. At contract signature: the measurement plane of the guaranteed MWh; the warranted curve at that plane; fixed-price augmentation options; warranty treatment of a blended fleet.
  2. At design freeze: pad, foundations, conduit and spare MV feeder positions; PCS and transformer headroom; a DC voltage window future blocks can match; interconnection filed for the full build-out.
  3. At COD: the commissioning capacity test that becomes the baseline; the augmentation reserve named in the financial model.
  4. Every operating year: state-of-health telemetry against the warranted curve; re-forecast the crossing; check the code edition and tariff landscape.
  5. At each crossing minus lead time: the order — this is the decide-by date the planner computes, and after it passes, every remaining option is worse.
Assumptions & sources

Every default, and where it comes from

Default Value Provenance
Degradation presets (0.25C / 0.5C / 1C) 21-point SOH and efficiency curves Illustrative — typical shape for LFP duty at each C-rate, not a warranty and not a vendor's schedule. Use your supplier's warranted curve for any commercial decision.
Reference plant 640 MWh at HV, 5.016 MWh blocks, events at years 10 and 15 A worked configuration for teaching, carried over from the model this planner is ported from; every number is replaceable above.
Loss chain BOL SOH 100%, SOC window 98%, DC 99.7%, PCS 98.2%, MV 99.0%, AC 99.5%, HV 99.5% — and the preset's efficiency curve, 96.9% at age zero on the 0.5C default Typical modern-plant values, illustrative. The seven editable factors multiply to 0.94 (BOL SOH contributes nothing at its 100% default); the preset's efficiency curve — applied in full at the DC plane, a conservatism carried from the reference model — takes it to ≈ 0.91 nameplate→HV on day one. Enter your own under “Show the loss chain & stranding check.”
Block cost and discount rate $0.55M, 6% Placeholders so the NPV arithmetic is visible. The tool publishes no prices and no price forecast — commercial numbers are yours to enter.
Procurement + outage lead 12 months Placeholder; use your supply chain's real figure.
Pack-price history ≈90% decline 2010→2025, ~$1,200/kWh → ~$108/kWh BNEF lithium-ion pack price survey — the same figures the glossary and the sizing article carry.
Strategy bands (0–5% / 30–40% / ~10%) see above Practitioner judgement — the author's operating rule of thumb, not a statistic.

Assumptions last reviewed 2026-08-11.

Use it in your work

Link or cite this tool

Free to use and link. Citation: BESS Augmentation Planner, BESS.courses — https://bess.courses/tools/bess-augmentation-planner/