1 The 400 MW site that was 40 MVA short
From projects across the instructor’s career. Names withheld.
- What happened
- The site was designed to deliver 400 MW at unity power factor, real power only, without working through what the grid operator would require. The design passed the customer’s due diligence, the supplier and the PCS manufacturer’s technical team.
- What it cost
- The supplier added 40 MVA of inverters at its own cost, about $3–4 million, and the customer’s site was a year late.
- What they didn’t know
- MW is not MVA. Inverters are rated in apparent power, and the reactive power the grid asks for at the connection point takes capacity away from MW.
- What would have caught it
- Sizing to the P-Q envelope at the point of interconnection, from the grid requirements and with transformer and cable losses included, at the offer stage.