Colombia (CREG 060/2019, red de 500 kV) ride-through requirements
High-voltage ride-through for Colombia. Every breakpoint below is read from the code itself, and carries the clause it came from — so you can check it, not just cite it.
What is the high-voltage ride-through envelope for Colombia (CREG 060/2019, red de 500 kV)?
The plant must ride through for any voltage that stays on or below this envelope. The envelope holds 1.2 pu from t = 0 to 2 s; then 1.05 pu from 2 s onward — the last band the envelope defines, with no stated end time.
Every breakpoint is stated in the clause cited below.
Applies to Wind + PV plants connected at 500 kV (STN)
| From | To | Voltage | Between the points |
|---|---|---|---|
| 0 | 2 s | 1.2 pu | Held flat |
| 2 s | no stated end | 1.05 pu | Held flat |
The clause this came from
Resolución CREG 060 de 2019, Artículo 14 — numeral 5.7 lit. c) del Código de Operación; figura 'Característica de LVRT y HVRT para plantas eólicas y solares fotovoltaicas con conexión a nivel de 500 kV' (official graphic obj_3.gif).
Who does Colombia (CREG 060/2019, red de 500 kV) bind, and since when?
Wind + PV plants connected at 500 kV (STN). No date of effect is published here — grid codes are reissued, so check the current issue before relying on it.
These figures are a reading aid, not legal advice. Grid codes are reissued: verify against the current edition before you design to them.
Digitised operating parameters beyond ride-through — droop, reactive capability, operating ranges — are published for 36 of the 66 codes in this atlas, not yet for Colombia (CREG 060/2019, red de 500 kV). That is a gap on this site, not a statement that Colombia (CREG 060/2019, red de 500 kV) sets none — the atlas hub marks the codes that carry them.
Curve data last checked against the code on — 66 standards, 130 envelopes, published by bess.engineer under CC BY 4.0.
Questions this page answers about Colombia (CREG 060/2019, red de 500 kV)
- Does Colombia (CREG 060/2019, red de 500 kV) require ride-through, or only that the plant does not trip?
- Ride-through. Every envelope on this page is a performance duty the plant must meet, not a protection-setting no-trip boundary — they are different obligations. That is what these curves are; they are not everything Colombia (CREG 060/2019, red de 500 kV) contains. The requirement sentence under each chart says which side of the curve is the compliant one.
- Are the numbers on this page taken from Colombia (CREG 060/2019, red de 500 kV) itself?
- Yes. Every breakpoint is read from the code, and each envelope carries the clause it came from, quoted in full under its chart — so you can check the figure against the standard rather than cite it from this page.
- Which events are charted for Colombia (CREG 060/2019, red de 500 kV)?
- Colombia (CREG 060/2019, red de 500 kV) is charted here with 1 envelope — high-voltage ride-through (HVRT). No low-voltage or frequency envelope is charted here — check Colombia (CREG 060/2019, red de 500 kV) itself before concluding it sets none.
Ride-through, in context.
An envelope is a compliance boundary; understanding why it exists is a different question. The ride-through and grid-forming entries cover the engineering, and the Engineering Foundations course builds it from the physics up.