Finnish strategic reserve
mechanism operational but zero capacity selected for both November 2024-October 2025 and November 2025-October 2026 periods
Fingrid holds competitively procured power plants or demand response outside normal markets for exceptional adequacy shortages.
periodic tender under Finnish strategic-reserve rules
- Unit of obligation
- maintain availability for exceptional activation while remaining outside normal market use as required
- Auction held in 2025
- No — No capacity auction for this market was found to have been held during 2025 in the sources reviewed.
Zero procurement means no selected reserve capacity, not abolition of the mechanism.
tendered availability remuneration if selected