AESO

Alberta, Canada.

Wholesale design: real-time energy-only power pool with a separate day-ahead operating-reserve exchange and contracted reliability services.

Operator
Alberta Electric System Operator
Nominal frequency
60 Hz
Where energy trades

Where does energy trade in AESO?

Energy in AESO trades in 2 layers: Alberta wholesale energy market and Operating Reserve market. Participation in Alberta wholesale energy market is mandatory. Scheduling and settlement, where the cited sources give them, are in the table below.

Layer Scheduling Settlement
Alberta wholesale energy market (mandatory) real-time merit-order dispatch uniform Alberta pool price under the ISO rules
Operating Reserve market day-ahead procurement in defined on-peak, off-peak, AM super-peak, and PM super-peak blocks active-reserve equilibrium price plus hourly pool price; standby reserve uses premium and activation-price components
What a battery can sell

What ancillary services can a battery sell in AESO?

AESO has 8 ancillary-service products, across 7 families — regulation, fast frequency response, contingency reserve, replacement reserve, reactive power & voltage, black start & restoration and other services: Blackstart Service, Fast Frequency Response, Load Shed Service for Imports, Regulating Reserve, Spinning Reserve, Supplemental Reserve, Transmission Must-Run Service, Voltage Regulation. Response timing, direction and eligibility for each are in the table below; a product's full record lists the official sources behind it.

Every value below comes from the official sources listed in that product's full record. Most products cite more than one, and the published sources do not say which of them states each individual value, so the binding is to the product's record rather than to a single document. A missing line means the source does not state that value — never that the value is zero.

Scroll the table sideways for the rest of the columns →

8 ancillary-service products in AESO, grouped into 7 families. Each row runs left to right through one product's life: how it activates, how quickly it has to respond, how long it has to keep delivering, and how it is bought.
Service How it activates Response Sustained delivery Procurement
Regulation
Regulating Reserve Response type pre-contingency continuous Trigger continuous movement within the contracted and dispatched regulating-reserve range Dispatched by automatic generation control and System Controller directive No deadline established Section 205.4 specifies performance and a minimum ramp capability of 10% of qualified regulating-reserve MW per minute; it does not support treating one fixed time as universal for every qualified range. Through day-ahead, active; day-ahead standby Pricing design Watt-Ex active or standby Operating Reserve settlement
Full record for Regulating Reserve — document bound, page for these figures not recorded
What it is for

Continuously balance short-term supply and demand and support frequency through automatic control.

What the source does not state

It does not state a response time or how long delivery has to be sustained, and the volume is either set per auction or not published as a standing figure — the source does not say which.

Sources
Fast frequency response
Fast Frequency Response FFR Response type post-contingency fast frequency Trigger contract-defined frequency trigger or qualifying system event; service remains available until released or for the rule-defined one-hour period Dispatched by automatic frequency response under a service contract and Section 205.9 No deadline established The response deadline is a contract parameter under Section 205.9; no single public value applies to every FFR procurement stream. Minimum obligation at least 1 h Through contract or pilot Pricing design contract-specific; a recurring Market-Based FFR process was being prepared in 2026
Full record for Fast Frequency Response — document bound, page for these figures not recorded
What it is for

Arrest and support recovery from rapid frequency decay following sudden loss of imports or internal generation.

Notes from the source

As of 2026-08-02, AESO described Market-Based FFR as preparing to launch. Existing FFR delivery through LSSi and other contracted arrangements is not an already-operating co-optimized spot market.

Checkpoint recap

Minimum sustained 1 h

What the source does not state

The source states a minimum delivery period. It does not state a response time or a maximum duration, and the volume is either set per auction or not published as a standing figure — the source does not say which.

Sources
Contingency reserve
Load Shed Service for Imports LSSi Response type post-contingency fast frequency Trigger loss of the Alberta-British Columbia intertie or another contract-defined event Dispatched by automatic or manual arming and tripping under the Import Load Shed Agreement Through competitive multi-year contract Pricing design contract-specific
Full record for Load Shed Service for Imports — document bound, page for these figures not recorded
What it is for

Trip or curtail contracted load after loss of an intertie so Alberta can securely carry a higher import transfer capability.

What the source does not state

It does not state a response time or how long delivery has to be sustained, and the volume is either set per auction or not published as a standing figure — the source does not say which.

Sources
Spinning Reserve Response type post-contingency Trigger synchronized generating capability or qualified load response that reaches the dispatched amount within ten minutes Dispatched by System Controller directive and inherent frequency response, as applicable Expected within 10 min Through day-ahead, active; day-ahead standby Pricing design Watt-Ex active or standby Operating Reserve settlement
Full record for Spinning Reserve — document bound, page for these figures not recorded
What it is for

Provide synchronized contingency reserve and immediate frequency support following an unexpected imbalance.

Checkpoint recap

Expected within 10 min

What the source does not state

The source states the response deadline. It does not state how long delivery has to be sustained, and the volume is either set per auction or not published as a standing figure — the source does not say which.

Sources
Replacement reserve
Supplemental Reserve Response type post-contingency Trigger qualified generation or load capability available within ten minutes under Section 205.6 Dispatched by System Controller directive Expected within 10 min Through day-ahead, active; day-ahead standby Pricing design Watt-Ex active or standby Operating Reserve settlement
Full record for Supplemental Reserve — document bound, page for these figures not recorded
What it is for

Provide contingency reserve from resources that need not already be synchronized.

Checkpoint recap

Expected within 10 min

What the source does not state

The source states the response deadline. It does not state how long delivery has to be sustained, and the volume is either set per auction or not published as a standing figure — the source does not say which.

Reactive power & voltage
Voltage Regulation Response type continuous or directed Trigger facility-specific voltage setpoint and reactive capability under Section 503.4 Dispatched by automatic voltage regulator and System Controller directive Through mandatory technical service, or directed Pricing design ISO tariff treatment, as applicable
Full record for Voltage Regulation — document bound, page for these figures not recorded
What it is for

Maintain system voltage through automatic voltage regulation and reactive-power capability.

What the source does not state

It does not state a response time or how long delivery has to be sustained, and the volume is either set per auction or not published as a standing figure — the source does not say which.

Sources
Black start & restoration
Blackstart Service Blackstart Response type restoration Trigger restoration-plan and facility-specific contractual performance Dispatched by System Controller restoration instruction Through contractual Pricing design competitive contract or bilateral terms
Full record for Blackstart Service — document bound, page for these figures not recorded
What it is for

Self-start without grid power and re-energize the transmission system during restoration.

What the source does not state

It does not state a response time or how long delivery has to be sustained, and the volume is either set per auction or not published as a standing figure — the source does not say which.

Sources
Other services
Transmission Must-Run Service TMR Response type preventive location-specific Trigger facility- and location-specific transmission reliability need Dispatched by AESO contract and System Controller directive Through bilateral or competitive contract; directed service, when required Pricing design contract-specific or tariff-directed compensation
Full record for Transmission Must-Run Service — document bound, page for these figures not recorded
What it is for

Keep location-specific generation online at directed output when transmission capability is insufficient for local demand or reliability.

What the source does not state

It does not state a response time or how long delivery has to be sustained, and the volume is either set per auction or not published as a standing figure — the source does not say which.

Sources
Getting paid to exist

Does AESO have a capacity mechanism?

No central capacity market. AESO has 1 capacity/adequacy arrangement — Energy-only resource adequacy framework — and it works differently.

Energy-only resource adequacy framework

Alberta continued to operate an energy-only wholesale market. The prior capacity-market initiative was cancelled in 2019. Government approved the Restructured Energy Market ISO rules in March 2026, with implementation targeted to begin in mid-2027, but REM did not create an operating capacity market or a 2025 capacity auction.

Auction held in 2025
No — No capacity auction for this market was found to have been held during 2025 in the sources reviewed.
Questions

Common questions about AESO

Who operates AESO?
Alberta Electric System Operator operates AESO, covering Alberta, Canada.
Was a qualifying capacity event held in AESO in 2025?
No. Energy-only resource adequacy framework: no qualifying 2025 event is recorded. No capacity auction for this market was found to have been held during 2025 in the sources reviewed.
How is energy traded, priced and settled in AESO?
AESO: real-time energy-only power pool with a separate day-ahead operating-reserve exchange and contracted reliability services.