In Western Australia's Wholesale Electricity Market, AEMO settles three main market revenue streams for a battery: energy in the Real-Time Market, the five Frequency Co-optimised Essential System Services (FCESS), and Capacity Credits under the Reserve Capacity Mechanism (it also pays any awards under the Supplementary Essential System Service Mechanism and any Non-Co-optimised Essential System Services contracts that AEMO procures). Most energy in the WEM is traded under bilateral contracts outside the market, and AEMO settles each participant's deviation from its net contract position, which it can adjust in the day-ahead Short-Term Energy Market. The duration a new battery must sustain to earn full capacity credit rose in 2025 and again in 2026, so the worked example sits there. Dollar figures are Australian dollars.
Registration, telemetry and settlement
The Electricity System and Market Rules (ESM Rules, formerly the WEM Rules) treat a battery as an Electric Storage Resource. A facility with a System Size of 10 MW or more must register as a Scheduled or Semi-Scheduled Facility, and one between 5 MW and 10 MW must apply to AEMO for an exemption if it does not register. At 10 MW or more a battery-only facility is normally registered as a Scheduled Facility, the class AEMO's design summary describes as fully controllable; a smaller one may register as Non-Scheduled. Its System Size counts both directions: the lesser of its Declared Sent Out Capacity and its output capability, plus the lesser of its Contract Maximum Demand and its charging capability.
AEMO sees the battery's stored energy directly. The Charge Level, in MWh, reaches AEMO through a real-time data feed under section 2.36A of the rules. AEMO dispatches energy and FCESS together in every five-minute Dispatch Interval. Energy settles at the Reference Trading Price, the time-weighted average of the six five-minute energy prices in each 30-minute Trading Interval, while each FCESS settles at its own five-minute Market Clearing Price.
Frequency services: accreditation first
A battery cannot offer FCESS until AEMO accredits the facility for each service it wants to sell: Regulation Raise, Regulation Lower, Contingency Reserve Raise, Contingency Reserve Lower and the RoCoF Control Service. An accredited contingency reserve provider must be able to sustain its response for at least 15 minutes after a contingency event, and a regulation provider must be able to deliver its full enabled MW at any time within the Dispatch Interval. Raise services draw down stored energy and lower services add to it, so a battery needs charge headroom in both directions for what it is enabled to provide; under clause 7.5.10 the participant for a battery-only Scheduled Facility can ask AEMO to build charge-level limits into dispatch.
By the third quarter of 2025, batteries supplied most regulation and contingency reserve. AEMO reported that after two more large batteries were accredited, batteries took 77% of combined regulation and contingency reserve volume that quarter, and that FCESS enablement costs had dropped as more batteries became accredited. The RoCoF Control Service was still supplied only by gas (63.1%) and coal (36.9%) facilities.
Worked example: Capacity Credits for a four-hour battery
Capacity Credits depend on certification. In the standard case, clause 4.11.3 sets a battery's Peak Certified Reserve Capacity at AEMO's reasonable expectation of the Linearly Derating Capacity it can sustain over the Peak Electric Storage Resource Obligation Duration, at 41°C ambient and net of any associated load. The rules define Linearly Derating Capacity as the lesser of nameplate MW and the maximum Charge Level in MWh divided by half the number of 30-minute Trading Intervals in that duration, which is the duration in hours.
The duration is the ESR Duration Requirement, fixed for each battery by the cycle in which it first receives Peak Capacity Credits: eight Trading Intervals (4 hours) up to the 2024 cycle and 12 Trading Intervals (6 hours) in the 2025 cycle, which covers the 2027-28 Capacity Year. The 2025 cycle's Peak Reserve Capacity Price is A$360,700 per MW per year. The table takes an illustrative 100 MW battery, with no associated load and no allowance for temperature de-rating, both of which would lower the certified MW.
Against full nameplate, the two extra hours cost the four-hour battery a third of its certified MW, about A$12.0 million a year at the 2025 cycle price. A battery keeps the requirement from the year it first received Capacity Credits for 10 Capacity Years, unless a later Facility Upgrade resets it. AEMO pays Peak Capacity Credits a daily price; for a new battery in 2027-28 the floating price is A$360,700 ÷ 366 Trading Days ≈ A$985.52 per MW per day (shown in AEMO's Request for Expressions of Interest as A$30,058 per MW per month).
Illustrative: certified capacity and annual value for a 100 MW battery (A$, 2025 cycle price), assuming every certified MW becomes an uncontracted Peak Capacity Credit at the floating price, before any refunds | Case | Certified MW = min(100, MWh ÷ hours) | Annual value at A$360,700/MW |
| 400 MWh, 2025 cycle (6 hours) | min(100, 400 ÷ 6) = 66.67 MW | A$24.05 million |
| 600 MWh, 2025 cycle (6 hours) | min(100, 600 ÷ 6) = 100 MW | A$36.07 million |
| 400 MWh under the 4-hour rule (cycles up to 2024) | min(100, 400 ÷ 4) = 100 MW | Earlier cycles carry their own prices |
| 400 MWh, 2026 cycle (7 hours) | min(100, 400 ÷ 7) = 57.14 MW | 2028-29 price not used here |
What changed recently
The duration requirement keeps rising. Under amended rules, AEMO's 2025 Electricity Statement of Opportunities set six hours for new batteries in the 2025 cycle, up from four, to cover the flatter residual peak that existing batteries had created. On recent high-demand days, AEMO found, batteries were largely exhausted by 8:30 pm even when fully charged before the peak. The June 2026 statement sets seven hours for 2028-29 and says the requirement may rise to about eight and a half hours later in the outlook period if anticipated capacity projects proceed.
The 2025 cycle also introduced Flexible Capacity, a separate credit for capacity that can start and ramp up within four hours, sized so the system can meet the largest forecast four-hour increase in demand. For 2027-28 it produced no additional payment, because the Flexible price came out below the Peak price. In the energy market, AEMO reported an average price of A$101.76/MWh in the third quarter of 2025, 27% above a year earlier, with a flatter daily profile. It noted that higher overnight and midday prices coincided with more battery charging, and lower morning and evening peaks with more battery discharge.