Forward Capacity Market
No primary Forward Capacity Auction was conducted in calendar 2025 because FCA 19 was delayed during the transition toward a prompt seasonal capacity design. Three annual and twelve monthly secondary reconfiguration-auction results published during 2025 are included below. FERC accepted the prompt-market design filing on 2026-03-30; the seasonal/accreditation reform track remained pending at the cutoff.
- Unit of obligation
- MW of capacity supply obligation
- Auction held in 2025
- Yes () — Dated from the publication of the auction results.