Australia (NER / AEMO) ride-through requirements

Low-voltage ride-through, High-voltage ride-through, Frequency ride-through for Australia. Every breakpoint below is read from the code itself, and where a point was taken off a published figure rather than stated in the clause, the section under that chart says so — an envelope that stops where its published chart stops.

3Envelopes
LVRT · HVRT · FRTEvents
Transmission & distribution Connection level
LVRT

What is the low-voltage ride-through envelope for Australia (NER / AEMO)?

The plant must ride through for any voltage that stays on or above this envelope. The envelope holds 0 pu from t = 0 to 430 ms; then 0.7 pu from 430 ms to 2 s; then 0.8 pu from 2 s to 10 s; then 0.9 pu from 10 s, plotted to 30 s.

The envelope stops where the published chart stops; the code states no end time.

Applies to Registered generating systems at any NEM connection point

Australia (NER / AEMO) — low-voltage ride-through envelopeAustralia (NER / AEMO) low-voltage ride-through envelope. The plant must ride through for any voltage that stays on or above the line; below it, the envelope no longer applies. Logarithmic time axis from 0.01 s to 50 s; linear voltage axis in per-unit. The first band applies from the instant of the event (t = 0). The envelope holds 0 pu from t = 0 to 430 ms; then 0.7 pu from 430 ms to 2 s; then 0.8 pu from 2 s to 10 s; then 0.9 pu from 10 s, plotted to 30 s. Stops where the published chart stops — the code states no end time.Australia (NER / AEMO) — low-voltage ride-through envelopeStops where the published chart stops — the code states no end timenominal 1.00 pu0.010.11100.000.200.400.600.801.001.20Time from event start (s, log scale) · first band applies from t = 0Voltage (pu)0.9 puplotted to 30 sMUST RIDE THROUGHmust ride through on or above the lineends at the plotted window, not a stated limit
Low-voltage ride-through envelope for Australia (NER / AEMO). Time runs on a logarithmic axis. Scroll the chart sideways for the rest of the time axis →
Low-voltage ride-through breakpoints for Australia (NER / AEMO)
From To Voltage Between the points
0 430 ms 0 pu Held flat
430 ms 2 s 0.7 pu Held flat
2 s 10 s 0.8 pu Held flat
10 s plotted to 30 s 0.9 pu Held flat
The clause this came from

NER as amended by the National Electricity Amendment (Improving the NEM access standards – Package 1) Rule 2025 No. 6 (ERC0393, final rule published 22 May 2025, in force 21 Aug 2025), item [176] substituting S5.2.5.5(c)(2)-(4) and (d)(1)-(9); item [174] substituting S5.2.5.4(a)(6),(7),(8); and NER Table S5.1a.2 column 4 (breaker-fail clearance times 175/250/430 ms). Sources: and NER Chapter 5 (Table S5.1a.2).

HVRT

What is the high-voltage ride-through envelope for Australia (NER / AEMO)?

The plant must ride through for any voltage that stays on or below this envelope. The envelope holds 1.3 pu from t = 0 to 200 ms; then 1.25 pu from 200 ms to 2 s; then 1.2 pu from 2 s to 20 s; then 1.15 pu from 20 s to 20 min; then 1.1 pu from 20 min onward — the last band the envelope defines, with no stated end time.

Every breakpoint is stated in the clause cited below.

Applies to Registered generating systems at any NEM connection point

Australia (NER / AEMO) — high-voltage ride-through envelopeAustralia (NER / AEMO) high-voltage ride-through envelope. The plant must ride through for any voltage that stays on or below the line; above it, the envelope no longer applies. Logarithmic time axis from 0.01 s to 5000 s; linear voltage axis in per-unit. The first band applies from the instant of the event (t = 0). The envelope holds 1.3 pu from t = 0 to 200 ms; then 1.25 pu from 200 ms to 2 s; then 1.2 pu from 2 s to 20 s; then 1.15 pu from 20 s to 20 min; then 1.1 pu from 20 min onward — the last band the envelope defines, with no stated end time (drawn as an open dashed tail).Australia (NER / AEMO) — high-voltage ride-through envelopenominal 1.00 pu0.010.111010010000.901.001.101.201.301.40Time from event start (s, log scale) · first band applies from t = 0Voltage (pu)1.1 puMUST RIDE THROUGHmust ride through on or below the lineopen — no stated end time
High-voltage ride-through envelope for Australia (NER / AEMO). Time runs on a logarithmic axis. Scroll the chart sideways for the rest of the time axis →
High-voltage ride-through breakpoints for Australia (NER / AEMO)
From To Voltage Between the points
0 200 ms 1.3 pu Held flat
200 ms 2 s 1.25 pu Held flat
2 s 20 s 1.2 pu Held flat
20 s 20 min 1.15 pu Held flat
20 min no stated end 1.1 pu Held flat
The clause this came from

NER S5.2.5.4(a)(1)–(6) as substituted by item [174] of the National Electricity Amendment (Improving the NEM access standards – Package 1) Rule 2025 No. 6 (ERC0393), in force 21 Aug 2025. Same list independently confirmed in the AEMC's ERC0222 generator technical performance standards pack.

FRT

What is the frequency ride-through envelope for Australia (NER / AEMO)?

The plant must ride through between the upper and lower bands. The upper (over-frequency) band holds 52 Hz from t = 0 to 2 min; then 51 Hz from 2 min to 10 min; then 50.5 Hz from 10 min, plotted to 20 min. The lower (under-frequency) band holds 47 Hz from t = 0 to 2 min; then 49 Hz from 2 min to 10 min; then 49.5 Hz from 10 min, plotted to 20 min.

The envelope stops where the published chart stops; the code states no end time.

Applies to Registered generating systems at any NEM connection point

Australia (NER / AEMO) — frequency ride-through envelopeAustralia (NER / AEMO) frequency ride-through envelope. The plant must ride through for any frequency that stays between the lower and upper bands. Logarithmic time axis from 10 s to 2000 s; linear frequency axis in hertz. The first band applies from the instant of the event (t = 0). upper (over-frequency) band: holds 52 Hz from t = 0 to 2 min; then 51 Hz from 2 min to 10 min; then 50.5 Hz from 10 min, plotted to 20 min. lower (under-frequency) band: holds 47 Hz from t = 0 to 2 min; then 49 Hz from 2 min to 10 min; then 49.5 Hz from 10 min, plotted to 20 min. Stops where the published chart stops — the code states no end time.Australia (NER / AEMO) — frequency ride-through envelopeStops where the published chart stops — the code states no end timenominal 50 Hz1010010004647484950515253Time from event start (s, log scale) · first band applies from t = 0Frequency (Hz)50.5 Hzplotted to 20 min49.5 Hzplotted to 20 minMUST RIDE THROUGHUpper band (over-frequency)Lower band (under-frequency)must ride through between the bandsends at the plotted window, not a stated limit
Frequency ride-through envelope for Australia (NER / AEMO). Time runs on a logarithmic axis. Scroll the chart sideways for the rest of the time axis →

Upper limit

Frequency ride-through breakpoints for Australia (NER / AEMO) — Upper limit
From To Frequency Between the points
0 2 min 52 Hz Held flat
2 min 10 min 51 Hz Held flat
10 min plotted to 20 min 50.5 Hz Held flat

Lower limit

Frequency ride-through breakpoints for Australia (NER / AEMO) — Lower limit
From To Frequency Between the points
0 2 min 47 Hz Held flat
2 min 10 min 49 Hz Held flat
10 min plotted to 20 min 49.5 Hz Held flat
The clause this came from

NER S5.2.5.3 as substituted by item [173] of the ERC0393 final rule — automatic access standard, read with the S5.2.5.3 definitions: 'transient frequency limit' and 'transient frequency time' mean 47.5 Hz and 9 seconds respectively; 'stabilisation time' and 'recovery time' mean the longest times allowable for the frequency of the power system to remain outside the operational frequency tolerance band and the normal operating frequency band respectively. AEMC Reliability Panel, Frequency Operating Standard effective 9 October 2023, Table A.3 (mainland, interconnected system — protected event and multiple contingency event: containment band 47.0–52.0 Hz; stabilisation band 49.5–50.5 Hz within 2 minutes; recovery band 49.85–50.15 Hz within 10 minutes), read with the mainland operational frequency tolerance band 49.0–51.0 Hz and normal operating frequency band 49.85–50.15 Hz; Tables A.6/A.7 for Tasmania (47.0–55.0 Hz).

Beyond ride-through

Operating requirements beyond the envelopes.

The envelopes above are what Australia (NER / AEMO) demands during a disturbance. The rows below are the same regime’s operating and fault-response requirements — reactive capability, frequency response, continuous operating range, ramp rate, RoCoF withstand and fault-current injection — each researched from the document its own row cites, separately from the plotted corpus. Every row carries its clause and a verbatim quote, so you can check it the same way.

Supplementary operating requirements for Australia (NER / AEMO)
Requirement What the code states Clause
Reactive capability at connection point (automatic access standard) Reactive capability ±0.395 × Pmax reactive power, both supplying and absorbing, continuously at the connection point at ANY level of active power (equivalent to ≈0.93 power factor at Pmax); full rectangle in P-Q for voltages within ±5% of the mid-point voltage; outside that band the supplying capability (over-voltage) or absorbing capability (under-voltage) decreases linearly to zero at the clause S5.1a.4 voltage limits (voltage-dependent shape, Figure S5.2.1) Binds a 'schedule 5.2 plant' — generating systems and integrated resource systems (BESS bidirectional plant) connecting under NER Chapter 5 — with all production units in service, measured at the connection point; this is the automatic access standard, negotiable down to the minimum access standard (S5.2.5.1(b1): no reactive capability required) via a negotiated access standard. The under-voltage absorbing-capability taper is stated in the same clause S5.2.5.1(a1) but is not carried in the quoted text. S5.2.5.1(a1)
The clause this row cites

S5.2.5.1(a1) — “ A schedule 5.2 plant, operating with all its production units in service at any level of active power and while meeting its other performance standards applicable to the voltage ranges specified below, must be capable of supplying or absorbing reactive power continuously at its connection point of the following amounts: (1) for a voltage range that is five percent of nominal voltage above and below the mid-point voltage, both supplying and absorbing an amount at least equal to the product of the maximum active power of the schedule 5.2 plant and 0.395; and (2) for a voltage range from the upper limit of the range described in paragraph (1) to the upper limit established under clause S5.1a.4 without a contingency event: (i) absorbing an amount at least equal to the product of the maximum active power of the schedule 5.2 plant and 0.395; and (ii) supplying an amount at least equal to the amount specified under sub-paragraph (i) at the upper limit of the voltage range in paragraph (1), decreasing linearly to zero at the upper limit established under clause S5.1a.4 without a contingency event (National Electricity Rules, Chapter 5, Version 251, accessed 2026-08-10)

Frequency response mode — settable droop and deadband ranges Frequency response Droop settable within 2% to 10%; deadband settable within 0 to ±1.0 Hz (asymmetric rise/fall settings permitted); response must commence with no delay beyond that required for stable operation or inherent in plant controls once frequency leaves the deadband Capability requirement on a schedule 5.2 plant (generating system or integrated resource system) operating in frequency response mode under the automatic access standard S5.2.5.11(b)(2) and negotiated access standards; droop is defined at the connection point as % frequency change / % power-transfer change on active power capability (S5.2.5.11(a)). S5.2.5.11(i)(1)–(2)
The clause this row cites

S5.2.5.11(i)(1)–(2) — “ (1) the change in power transfer must occur with no delay beyond that required for stable operation, or inherent in the plant controls, once the frequency of the power system as measured at the connection point leaves a deadband around 50 Hz; (2) a schedule 5.2 plant must be capable of setting the deadband and droop within the following ranges: (i) the deadband referred to in subparagraph (1) must be set within the range of 0 to ± 1.0 Hz. Different deadband settings may be applied for a rise or fall in the frequency of the power system as measured at the connection point; and (ii) the droop must be set within the range of 2% to 10%, or such other settings as agreed with the Network Service Provider and AEMO; (National Electricity Rules, Chapter 5, Version 251, accessed 2026-08-10)

Mandatory primary frequency response — operational deadband Frequency response Deadband = PFCB = 49.985 Hz to 50.015 Hz (±0.015 Hz around 50 Hz), applied at the connection point; a narrower deadband is permitted with AEMO's agreement Binds each 'Affected Unit' — scheduled generating unit, semi-scheduled generating unit or scheduled bidirectional unit (i.e. scheduled BESS) of a Scheduled/Semi-Scheduled Generator or Scheduled Integrated Resource Provider — under AEMO's Primary Frequency Response Requirements made under NER 4.4.2A(a); subject to AEMO-granted variations/exemptions. PFRR Section 3.2.1 (PFCB defined in Section 1.2.1)
The clause this row cites

PFRR Section 3.2.1 (PFCB defined in Section 1.2.1) — “ Subject to section 3.2.2 and any variation or exemption granted in accordance with these PFRR, an Affected Unit must be operated with a deadband equal to the PFCB. For the avoidance of doubt, the Affected Unit’s deadband applies at the connection point. […] PFCB: Primary frequency control band (as at 8 May 2023, it is 49.985 Hz to 50.015 Hz). (Primary Frequency Response Requirements (made under NER clause 4.4.2A(a)), accessed 2026-07-28)

Mandatory primary frequency response — droop Frequency response Droop ≤ 5% at the connection point, computed as 100 × (ΔF/50)/(ΔP/PMAX) with ΔF measured beyond the deadband edge and PMAX = Maximum Operating Level; may be asymmetrical for over-/under-frequency Binds all Affected Units (scheduled generating units, semi-scheduled generating units and scheduled bidirectional units, i.e. scheduled BESS) under AEMO's PFRR v3.0 made under NER 4.4.2A(a), subject to variation or exemption. The droop formula, the PMAX definition and the asymmetry permission are transcribed from PFRR Equation 1 and its surrounding Section 3.3 text but are not carried in the quoted text. PFRR Section 3.3
The clause this row cites

PFRR Section 3.3 — “ For all Affected Units, subject to any variation or exemption granted in accordance with these PFRR, droop at the connection point must be set to less than or equal to 5%. The change in frequency is to be measured from the upper or lower limit (as applicable) of the Affected Unit deadband, as shown in Equation 1. (Primary Frequency Response Requirements (made under NER clause 4.4.2A(a)), accessed 2026-07-28)

Mandatory primary frequency response — response time Frequency response ≥5% of PMAX active-power change within ≤10 s of a frequency step beyond the deadband (step ≤0.5 Hz); response must commence with no delay beyond that inherent in the plant and plant controls; faster response explicitly acceptable Binds Affected Units (including scheduled bidirectional units / BESS) under AEMO's PFRR v3.0; response time measured from frequency crossing the deadband limit until active power reaches a 5% change based on PMAX. PFRR Section 3.4
The clause this row cites

PFRR Section 3.4 — “ Subject to any variation or exemption granted in accordance with these PFRR, an Affected Unit should be capable of achieving a 5% change in active power output within no more than 10 seconds, resulting from a sufficiently large positive or negative step change in frequency greater than the Affected Unit’s deadband and less than or equal to 0.5 Hz. (Primary Frequency Response Requirements (made under NER clause 4.4.2A(a)), accessed 2026-07-28)

Continuous frequency operating ranges (automatic access standard) Continuous operating range Continuous uninterrupted operation: indefinitely within the normal operating frequency band; between the normal operating frequency band and the operational frequency tolerance band (either side) for at least the recovery time; and between the operational frequency tolerance band and the extreme frequency excursion tolerance limits (either side) for at least the stabilisation time. Band values are set by the Frequency operating standard, Table A.1 - mainland (Normal conditions): normal operating frequency band 49.85-50.15 Hz, operating frequency tolerance band (Table A.1's printed label for the NER's 'operational frequency tolerance band') 49.0-51.0 Hz, extreme frequency excursion tolerance limit 47.0-52.0 Hz; Tasmania: 49.85-50.15 Hz / 48.0-52.0 Hz / 47.0-55.0 Hz; mainland island-condition normal operating frequency band 49.5-50.5 Hz. Binds every schedule 5.2 plant at the connection point - generating systems, integrated resource systems and (where applicable) synchronous condensers. Storage is bound explicitly: NER Chapter 10 defines production unit as including bidirectional units (the Chapter 10 definitions are cited but not quoted here; Chapter 10 PDF pp. 97-98), so a grid-scale BESS connects as an integrated resource system whose bidirectional units are production units. S5.2.5.3(a)(1) reads each band as 'the widest range specified for those terms for any condition (including an "island" condition)' in the frequency operating standards for the region, so island/system-restoration columns of Table A.1 can set the governing width; S5.2.5.3(a)(2) defines stabilisation time and recovery time as the longest times allowable for system frequency to remain outside the operational frequency tolerance band and the normal operating frequency band respectively. This is the automatic access standard; the minimum access standard (S5.2.5.3(c)) is narrower and the plant may agree a negotiated access standard between the two. NER Schedule 5.2, clause S5.2.5.3(b) (automatic access standard), read with S5.2.5.3(a)(1)-(2) + Frequency operating standard (effective 9 October 2023), Appendix A.1, Table A.1 'Frequency bands'
The clauses this row cites

NER Schedule 5.2, clause S5.2.5.3(b) (automatic access standard), read with S5.2.5.3(a)(1)-(2) — “ The automatic access standard is a schedule 5.2 plant and each of its production units, and (where applicable) synchronous condensers, must remain in continuous uninterrupted operation for frequencies in the following ranges: (1) the lower bound of the extreme frequency excursion tolerance limits to the lower bound of the operational frequency tolerance band for at least the stabilisation time; (2) the lower bound of the operational frequency tolerance band to the lower bound of the normal operating frequency band, for at least the recovery time including any time spent in the range under subparagraph (1); (3) the normal operating frequency band for an indefinite period; (4) the upper bound of the normal operating frequency band to the upper bound of the operational frequency tolerance band, for at least the recovery time including any time spent in the range under subparagraph (5); and (5) the upper bound of the operational frequency tolerance band to the upper bound of the extreme frequency excursion tolerance limits for at least the stabilisation time, unless the rate of change of frequency is outside the range of –4 Hz to 4 Hz per second for more than 0.25 seconds, -3 Hz to 3 Hz per second for more than one second, or such other range as determined by the Reliability Panel from time to time. (National Electricity Rules, Chapter 5, Version 251, accessed 2026-08-08)

Frequency operating standard (effective 9 October 2023), Appendix A.1, Table A.1 'Frequency bands' — “ [Table A.1 transcription - rows as printed] normal operating frequency band: Normal (Hz) Mainland/Tasmania (spanned cell) 49.85 – 50.15; Island (Hz) Mainland 49.5 – 50.5, Tasmania 49.0 – 51.0; System restoration (Hz) Mainland 49.5 – 50.5. operating frequency tolerance band: Normal Mainland 49.0 – 51.0, Tasmania 48.0 – 52.0; Island Mainland 49.0 – 51.0, Tasmania 48.0 – 52.0; System restoration Mainland 49.0 – 51.0. extreme frequency excursion tolerance limit: Normal Mainland 47.0 – 52.0, Tasmania 47.0 – 55.0; Island Mainland 47.0 – 52.0, Tasmania 47.0 – 55.0; System restoration Mainland 47.0 – 52.0. (Frequency operating standard - Reliability Panel AEMC, effective 9 October 2023, accessed 2026-08-08)

Continuous and time-limited voltage ranges (automatic access standard) Continuous operating range At the connection point (RMS, % of nominal voltage): 90% to 110% continuously (subject to S5.2.5.4(e1)/(e3)); time-limited continuous-operation bands: at least marginally over 130% for ≥0.02 s, over 125% up to 130% for ≥0.2 s, over 120% up to 125% for ≥2 s, over 115% up to 120% for ≥20 s, over 110% up to 115% for ≥20 min (all after T(ov)); below 90% down to 80% for ≥10 s and below 80% down to 70% for ≥2 s (after T(uv)). Binds every schedule 5.2 plant (generating systems and integrated resource systems, i.e. BESS, plus synchronous condensers) and each of its operating production units at the connection point; per S5.2.5.4(a0)(3) voltages are RMS power-frequency values, phase-to-phase or phase-to-ground, as a percentage of nominal voltage. Within the 90-110% continuous band, (e1) requires (for up to 10% voltage variation) that active power output not reduce and that reactive capability per the S5.2.5.1 performance standard be maintained. The minimum access standard (S5.2.5.4(b)) is narrower (e.g. 115-120% only ≥0.1 s, 110-115% ≥0.9 s, 80-90% ≥5 s, plus V/f-ratio limits of 1.15 for max 2 min and 1.10 for max 10 min). This is the operating-voltage window; the multi-disturbance fault ride-through regime is S5.2.5.5 (covered by the ride-through curves published for this code, not repeated here). The minimum-access-standard thresholds (S5.2.5.4(b), document p. 822) and the S5.2.5.4(e1) no-power-reduction requirement with its 10% figure are cited but not carried in the quoted text. NER Schedule 5.2, clause S5.2.5.4(a) (automatic access standard), read with S5.2.5.4(a0)
The clause this row cites

NER Schedule 5.2, clause S5.2.5.4(a) (automatic access standard), read with S5.2.5.4(a0) — “ The automatic access standard is a schedule 5.2 plant and each of its operating production units and synchronous condensers must remain in continuous uninterrupted operation where a power system disturbance external to the plant causes the voltage on one or more phases at the connection point to vary within the following ranges: (1) at least marginally exceeding 130% of nominal voltage for a period of at least 0.02 seconds after T(ov); (2) over 125% up to and including 130% of nominal voltage for a period of at least 0.2 seconds after T(ov); (3) over 120% up to and including 125% of nominal voltage for a period of at least 2 seconds after T(ov); (4) over 115% up to and including 120% of nominal voltage for a period of at least 20 seconds after T(ov); (5) over 110% up to and including 115% of nominal voltage for a period of at least 20 minutes after T(ov); (6) subject to paragraphs (e1) and (e3), 90% to 110% of nominal voltage continuously; (7) below 90% down to and including 80% of nominal voltage for a period of at least 10 seconds after T(uv); and (8) below 80% down to and including 70% of nominal voltage for a period of at least 2 seconds after T(uv). (National Electricity Rules, Chapter 5, Version 251, accessed 2026-08-08)

Minimum dispatch ramp rate (bid ramp-rate floor) Ramp rate Up and down ramp rates offered to AEMO must be at least the 'minimum ramp rate requirement' = the LOWER of 3 MW/minute or 3% of maximum generation/consumption per minute (rounded down to whole MW/min; floor of 1 MW/minute if rounding gives zero), applied separately to generation and consumption Market/dispatch obligation (tier 1 civil penalty provision) on Market Participants for each scheduled generating unit, scheduled bidirectional unit (generation and consumption, i.e. scheduled BESS) and scheduled load — a floor on bid ramp rates, not a connection-point gradient cap; the NER states no maximum ramp limit beyond the participant-declared physical maximum under 3.13.3(b). 3.8.3A(b)(1) + Chapter 10, definition of 'minimum ramp rate requirement'
The clauses this row cites

3.8.3A(b)(1) — “ a Market Participant to which this clause 3.8.3A applies must provide an up ramp rate and a down ramp rate to AEMO for each generating unit, scheduled bidirectional unit (in respect of generation and consumption), scheduled network service and/or scheduled load that is: (1) at least the minimum ramp rate for the scheduled resource (National Electricity Rules, Version 251 — clause 3.8.3A and Chapter 10 glossary, accessed 2026-07-28)

Chapter 10, definition of 'minimum ramp rate requirement' — “ (a) In relation to a generating unit, bidirectional unit, voluntarily scheduled resource or scheduled load, for each of generation and consumption (as applicable), means the lower of: (1) 3 MW/minute; or (2) 3% of the maximum generation or consumption (as applicable) provided in accordance with clause 3.13.3(b), expressed as MW/minute and rounded down to the nearest whole number except where the result would be zero, in which case the minimum ramp rate requirement is 1 MW/minute. (National Electricity Rules — Chapter 10 glossary (M), accessed 2026-07-28)

RoCoF ride-through — automatic access standard RoCoF withstand Continuous uninterrupted operation required unless RoCoF exceeds ±4 Hz/s for more than 0.25 s, or ±3 Hz/s for more than 1 s (i.e. must withstand up to ±4 Hz/s for 0.25 s and ±3 Hz/s for 1 s) Automatic access standard binding a schedule 5.2 plant and each of its production units (generating systems and integrated resource systems / BESS) across the frequency ranges of the regional frequency operating standards; the Reliability Panel may determine other ranges. S5.2.5.3(b)
The clause this row cites

S5.2.5.3(b) — “ The automatic access standard is a schedule 5.2 plant and each of its production units, and (where applicable) synchronous condensers, must remain in continuous uninterrupted operation for frequencies in the following ranges: […] unless the rate of change of frequency is outside the range of –4 Hz to 4 Hz per second for more than 0.25 seconds, -3 Hz to 3 Hz per second for more than one second, or such other range as determined by the Reliability Panel from time to time. (National Electricity Rules, Chapter 5, Version 251, accessed 2026-08-10)

RoCoF ride-through — minimum access standard RoCoF withstand Continuous uninterrupted operation required unless RoCoF exceeds ±2 Hz/s for more than 0.25 s, or ±1 Hz/s for more than 1 s (i.e. must withstand up to ±2 Hz/s for 0.25 s and ±1 Hz/s for 1 s) Minimum (lowest negotiable) access standard for a schedule 5.2 plant and each of its production units; an agreed performance standard must sit at or above this level. S5.2.5.3(c)
The clause this row cites

S5.2.5.3(c) — “ unless the rate of change of frequency is outside the range of -2 Hz to 2 Hz per second for more than 0.25 seconds, -1 Hz to 1 Hz per second for more than one second or such other range as determined by the Reliability Panel from time to time. (National Electricity Rules, Chapter 5, Version 251, accessed 2026-08-10)

Fault reactive-current injection capability (automatic access standard, asynchronous units) Fault-current injection Capability basis, at the connection point: positive-sequence capacitive reactive current, additional to the pre-disturbance level, of at least 4% of the maximum continuous current of all operating asynchronous production units per 1% reduction of positive-sequence voltage below the response-commencement voltage; at least 6% per 1% increase above the commencement voltage (inductive); plus negative-sequence current or equivalent to oppose unbalanced voltages. Response must commence when or before voltage reaches 85% (under-voltage) / 115% (over-voltage) of nominal, must start within 10 ms of the initiating condition, and for a step-like voltage profile the positive-sequence reactive current rise time must be no greater than 40 ms. Automatic access standard for 'a production system to the extent it comprises asynchronous production units' (S5.2.5.5A(c)(2)) - NER Chapter 10 defines 'production system' as including an integrated resource system to the extent of its production units, and 'production unit' as including bidirectional units, so inverter-based BESS is bound explicitly. The 4%/6% figures are minimum capability ('have facilities capable of'); the actually delivered response, within that capability range, is agreed with the Network Service Provider and AEMO at levels consistent with achieving the control objective (minimising per-phase voltage deviation while maintaining stable control). Current availability/priority is in S5.2.5.5A(i): the plant must keep available the maximum continuous current for connection-point voltages below 85% of nominal, and sufficient current for rated apparent power above 115%, except that AEMO and the NSP may agree limits on active current injection. Exemption (h)(2): no capacitive response required when the plant has no step-up/connection transformer and connection-point voltage is at or below 5% of nominal. The S5.2.5.5A(i) current-availability rule and the S5.2.5.5A(h)(2) exemption are cited but not carried in the quoted text. NER Schedule 5.2, clause S5.2.5.5A(f)(1) (automatic access standard - asynchronous plant) + NER Schedule 5.2, clause S5.2.5.5A(g)(1)-(2)
The clauses this row cites

NER Schedule 5.2, clause S5.2.5.5A(f)(1) (automatic access standard - asynchronous plant) — “ Subject to paragraph (h), a schedule 5.2 plant, for disturbances caused by a type of fault described in clause S5.2.5.5(c)(2) to (4), must: (1) to assist the maintenance of power system voltages during the disturbance, have facilities capable of supplying or absorbing at the connection point: (i) positive sequence capacitive reactive current in addition to its pre-disturbance level of at least 4% of the maximum continuous current of all operating asynchronous production units (in the absence of a disturbance) for each 1% reduction of positive sequence voltage at the connection point below the voltage at which the reactive current response commences; (ii) positive sequence inductive reactive current in addition to its pre-disturbance level of at least 6% of the maximum continuous current of all operating asynchronous production units (in the absence of a disturbance) for each 1% increase of positive sequence voltage at the connection point above the relevant percentage of nominal voltage at which the reactive current response commences; and (iii) negative sequence current or equivalent contributions to oppose unbalanced voltages during a disturbance … (within the range of capabilities expressed in this paragraph (f)(1)) to be agreed with the Network Service Provider and AEMO at levels consistent with achieving the control objective (National Electricity Rules, Chapter 5, Version 251, accessed 2026-08-08)

NER Schedule 5.2, clause S5.2.5.5A(g)(1)-(2) — “ For the purpose of paragraph (f): (1) the schedule 5.2 plant must commence the required response when or before the voltage reaches the following initiating conditions: (i) for an under-voltage disturbance, 85% of nominal voltage; or (ii) for an over-voltage disturbance, 115% of nominal voltage, with the specific response initiating conditions being agreed with the Network Service Provider and AEMO, consistent with achieving the control objective; and (2) the positive sequence reactive current response opposing the voltage change must commence within 10 milliseconds of the response initiating conditions being met, be adequately controlled and, for a step-like voltage profile at the connection point, have a positive sequence reactive current rise time of no greater than 40 milliseconds. (National Electricity Rules, Chapter 5, Version 251, accessed 2026-08-08)

Scope

Who does Australia (NER / AEMO) bind, and since when?

Registered generating systems at any NEM connection point. The FRT clause quoted above carries the date of effect — "effective 9 October 2023".

These figures are a reading aid, not legal advice. Grid codes are reissued: verify against the current edition before you design to them.

Curve data last checked against the code on — 66 standards, 130 envelopes, published by bess.engineer under CC BY 4.0.

Questions

Questions this page answers about Australia (NER / AEMO)

Does Australia (NER / AEMO) require ride-through, or only that the plant does not trip?
Ride-through. Every envelope on this page is a performance duty the plant must meet, not a protection-setting no-trip boundary — they are different obligations. That is what these curves are; they are not everything Australia (NER / AEMO) contains. The requirement sentence under each chart says which side of the curve is the compliant one.
Are the numbers on this page taken from Australia (NER / AEMO) itself?
Every breakpoint is read from the code, and where a point was taken off a published figure rather than stated in the clause, the section under that chart says so — on this page that includes an envelope that stops where its published chart stops. The clause each curve came from is quoted under it.
Which events are charted for Australia (NER / AEMO)?
Australia (NER / AEMO) is charted here with 3 envelopes — low-voltage ride-through, high-voltage ride-through, frequency ride-through (LVRT, HVRT, FRT).
Related

Ride-through, in context.

An envelope is a compliance boundary; understanding why it exists is a different question. The ride-through and grid-forming entries cover the engineering, and the Engineering Foundations course builds it from the physics up.

Elsewhere in Asia-Pacific: China (GB/T 36547-2024), India (CEA Connectivity Regs), Malaysia (Grid Code Additional Code 2025), New Zealand (EIPC cl 8.25A), New Zealand North Island (EIPC cl 8.19(1)), New Zealand North Island (EIPC cl 8.25A), and 9 more