Swedish strategic reserve
first 2025/26 tender cancelled because all bids exceeded the cap; re-tender launched in 2025 and 350 MW contracted from 15 January to 15 March 2026
Svenska kraftnät procures an out-of-market reserve for winter adequacy under EU-approved rules.
competitive tender up to a specified volume and price cap
- Unit of obligation
- remain available for exceptional activation during contracted winter dates
- Auction held in 2025
- No — The 2025 process was cancelled or produced no held auction.
Nordic mFRR and FCR are normal balancing markets.
tendered availability payment; final re-tender contract price was not disclosed in the cited announcement