Voltage drop
Voltage drop is the I × R — on AC, I × Z — that every ampere leaves behind in the conductors between two points of a plant, so the receiving end always sees less voltage than the sending end while current flows.
In a grid-scale BESS two runs carry the consequences: the DC cabling between battery terminals and PCS, where the drop compresses the usable voltage window at exactly the high-current moments the window is already tight, and the AC path from PCS through transformer to the point of interconnection, where collection-system drop and transformer regulation separate what the inverter makes from what the meter records.
The physics is elementary — Ohm's law applied to a length of conductor — but the consequences land at the two places the project's guarantees are written: the PCS DC terminals, where the datasheet window is defined, and the POI, where contract performance is measured. Managing it is a three-lever trade: conductor cross-section, run length, and above all the voltage class the current flows at.
Reviewed August 2026 by Sergey Syrvachev
New to BESS? Start free with the 7-email fundamentals course — no cost, no account.
What it is (precise)
On a DC run the drop is ΔV = I × R, with R the resistance of the whole current loop — out on one conductor and back on the other, so a 50 m run is 100 m of conductor — set by resistivity, length and cross-section. On an AC feeder the conductor's reactance joins in: the per-phase drop is approximately I × (R cos φ + X sin φ), which is why an AC drop calculation needs the power factor and why a heavily reactive dispatch drops more voltage through the same cable than a unity-power-factor one.
The law itself has its own entry under Ohm's law; this page is where the law meets the plant's conductor schedule, because every run on the single-line diagram — busbar, DC cable, LV bus, MV feeder, transformer winding — is a resistance or impedance in series with the power flow, and each one takes its volts in proportion to the current of the moment.
The same ampere costs the same volts wherever it flows, but the volts matter differently by level, which is why drop is judged as a percentage of the local bus. At fixed power, current scales as 1/V, so the absolute drop through a given conductor scales as 1/V and the percent drop as 1/V² — the arithmetic behind every step-up decision the plant makes, and behind the DC bus's own climb from 1000 to 1500 V, where the 1500 VDC entry works the numbers: two-thirds the current, and a percent drop that lands at 4/9 through the same copper.
The other discipline is the reference point. A voltage specification is meaningless without a location attached: the PCS voltage window is defined at the PCS DC terminals, contract performance is measured at the POI, and the battery vendor's voltage tables describe the rack terminals. Voltage drop is precisely the difference between those locations, so any check that compares numbers from two of them without the conductor run in between has assumed the drop is zero.
The DC run: battery terminals to PCS
Both bounds of the PCS voltage window are defined at the PCS DC terminals, so the cable between container and PCS narrows the usable window from both ends. Discharging, current flows from battery to PCS and the PCS sees the string voltage minus the cable drop — pressure on the floor.
Charging, the PCS must hold its terminals above the string by the same drop to push current in — pressure on the ceiling. The compression is proportional to current, so it is largest at exactly rated power, and it vanishes at rest — which is why a commissioning voltage check at low current proves nothing about the corners.
The currents are large enough for single volts per milliohm. A 314 Ah string at 0.5C carries about 157 A, and the paralleled bus of a 5 MWh-class container — on the order of a dozen strings — runs near 1,900 A at the same rate, so every milliohm of loop resistance between battery and PCS costs roughly 1.9 V at rated current.
Through the half-milliohm DC path in the 1500 VDC entry's worked example, 2,000 A leaves 1.0 V behind — about 0.07% of the bus. Small percentages, but they subtract from a window margin that is itself measured in tens of volts at the corners, and they recur at both ends of every cycle.
Where the DC drop actually binds is the cold, low-state-of-charge, high-current discharge — the corner the VDC window entry maps, where cold loaded sag sets the floor. Most of that sag comes from inside the cells: internal resistance drops roughly 40 mV per cell at 0.5C in the internal-resistance entry's worked example, and 0.1 V per cell is about 42 V at the terminals of a 416S string, growing as cold cuts electrolyte conductivity by roughly an order of magnitude between +25 C and -20 C.
The cable is the one term in that stack the designer fully controls — copper resistance actually falls slightly in the cold, around 0.4% per degree C, while the cells' resistance climbs — so conductor sizing cannot rescue a cold string, but an undersized run stacks avoidable volts onto the plant's worst corner at the exact hour the dispatch needs the floor to hold.
The governing relations are ΔV = I × R over the full loop on DC — both conductors — and approximately I × (R cos φ + X sin φ) per phase on AC, where power factor enters. The drop compresses the usable DC window from both ends, because both PCS bounds are defined at ITS terminals: discharge drop presses the floor and charge drop presses the ceiling, most at rated current. The scale of the currents makes the milliohms matter — about 1,900 A on a dozen-string 5 MWh-class bus is roughly 1.9 V per milliohm of loop resistance — and the binding corner is cold, low-SOC, high-current discharge, where cell-internal sag sets the floor and the cable drop stacks on top. The cable is the one term the designer fully controls. On the AC side the same logic picks the voltage for distance: a 3,600 kVA block is about 3,000 A at 690 V and 60 A at 34.5 kV, which is why LV runs are metres long. The largest single series impedance between PCS and POI is the transformer's nameplate per-cent impedance, and it moves with both real and reactive dispatch.
- Governing relations
- DC: ΔV = I × R over the full loop (both conductors). AC per phase: ≈ I × (R cos φ + X sin φ) — power factor enters on the AC side
- Scaling with voltage class
- At fixed power, current falls as 1/V, absolute drop as 1/V, percent drop as 1/V² — the arithmetic behind stepping up, and behind 1000 → 1500 VDC
- DC window compression
- Both PCS bounds are defined at its DC terminals: discharge drop presses the floor, charge drop presses the ceiling — the usable window narrows by I × R at both ends, most at rated current
- DC current scale
- ~157 A per 314 Ah string at 0.5C; ~1,900 A on a dozen-string 5 MWh-class bus — roughly 1.9 V per milliohm of loop resistance at that current
- Binding corner
- Cold, low-SOC, high-current discharge — cell-internal sag sets the floor and the cable drop stacks on top; the cable is the one term the designer fully controls
- AC current scale
- A 3,600 kVA block is ~3,000 A at 690 V but ~60 A at 34.5 kV — why LV runs are metres long and site distances are covered at MV
- Transformer regulation
- The nameplate percent impedance is a series drop under load — the largest single impedance between PCS and POI, moving with both real and reactive dispatch
- Not the same as
- I²R losses (the heat and energy half of the same current), internal resistance (the drop inside the cells), the VDC window itself (the bounds the drop presses against)
The AC side: PCS to POI
The AC story is dominated by one step change in current. A PCS block quoted at 3,600 kVA moves roughly 3,000 A of line current at its 690 V terminals — which is why the low-voltage bus is metres long and the step-up transformer sits on the same skid or pad as the inverter.
After step-up to a 34.5 kV collection level the same power is about 60 A, and feeders can cross hundreds of metres of site for a drop that would be intolerable at LV. That is the transmission-voltage argument scaled down to inside the fence: current falls as 1/V, load loss as 1/V², and the layout of a BESS site — short LV jumps, MV for every real distance — is that arithmetic drawn as a plan view.
The transformer itself is the largest single impedance in the chain. Its nameplate percent-impedance figure is a series impedance like any conductor's, and under load it drops voltage through the same I × (R cos φ + X sin φ) mechanism — the transformer-regulation face of voltage drop — so the MV-side voltage moves with both the magnitude and the direction of the plant's real and reactive dispatch.
That is why the load-flow study models the full chain, PCS terminals through transformer and collection feeders to the POI, at the corners of the P-Q envelope: reactive export raises the local LV voltage against a fixed grid, absorption lowers it, and the plant must still meet its voltage and reactive obligations at the POI, where performance is measured — not at the inverter.
On a multi-skid site the drop also differs by position along a feeder, so PCS units at the far end operate at a measurably different terminal voltage than those near the substation, which matters when every unit is asked for the same reactive contribution.
How it shows up in specs, studies and contracts
On the DC side the drop hides inside the battery-PCS pairing check: the worst-case loaded string minimum must clear Vdc_min plus the cable drop at maximum discharge current, and the charge peak must clear Vdc_max minus the same allowance. That calculation is only as good as its inputs, so the one-line diagram and DC cable schedule must carry the real conductor lengths and cross-sections behind it — a drop computed from a layout sketch that the civil design later stretched is a window margin that no longer exists.
The cable-sizing calculation runs at rated current with temperature-corrected conductor resistance, and commissioning can verify it directly: measure the voltage at both ends of a run at a known current and the difference is the as-built resistance, joints included — the same joints whose heating belongs to the I²R losses entry.
In studies and contracts the two sides separate. The DC drop feeds the battery-PCS envelope check and, through it, the capacity test: the witnessed test runs to a defined end-of-discharge, and if the PCS reaches its floor early because the cable drop was underestimated, the plant fails a test the cells could have passed.
The AC drop feeds the load-flow and reactive-capability studies at the POI, where the interconnection agreement holds the plant to voltage and power-factor obligations. Efficiency guarantees count the energy half of the same current — the I²R heat — but the voltage half is what decides whether rated power is deliverable at all at the corners, and the two halves are settled in different documents against different penalties.
Common pitfalls
The first trap is filing voltage drop under efficiency and moving on. The energy cost is the I²R half and it is genuinely small — fractions of a percent on a well-sized run. The expensive half is positional: the same few volts, subtracted at the PCS terminals at maximum current, compress the operating window at the corner where the capacity test ends and the winter dispatch strains, and no efficiency line item captures that.
The related error is computing the drop at an average or nominal current: drop scales linearly with current, so a figure quoted at typical dispatch understates the corner by the full ratio of peak to average — and the corner is also where the string is coldest and lowest, with the least margin to give.
The remaining traps are reference-point mixups. Comparing battery terminal voltage directly against a PCS window defined at the PCS DC terminals flatters the margin by exactly the cable drop, in both directions — the check must be run for the charge ceiling as well as the discharge floor, because the drop presses on both.
Quoting a drop in volts without naming the bus invites the wrong judgment: 1 V is noise at 34.5 kV and real margin at the DC floor. And on DC, forgetting that the loop is two conductors halves the computed resistance of every run. Each is an arithmetic slip; each survives every review that checks quantities but not locations.
Voltage drop is an efficiency issue — a fraction of a percent of energy on a properly sized cable, so once the losses are acceptable the design is done.
In reality: The energy is the small half, and it belongs to I²R losses. The half that costs projects money is where the volts go missing: subtracted at the PCS DC terminals at maximum current, the drop compresses the operating window at both ends — floor on discharge, ceiling on charge — and it is largest at exactly the cold, low-SOC corner where cell sag has already spent most of the margin. A cable that passes every efficiency check can still end the witnessed capacity test early by letting the PCS reach its floor before the battery is empty. On the AC side the same logic repeats at the POI: the meter that settles the contract sits on the far side of the transformer and collection drops, and a plant judged at its inverter terminals is being judged in the wrong place.
- VDC window Glossary
- I²R losses Glossary
- BESS Single-Line Diagram: How a Plant Is Wired Article
- Interactive: Energy Station Structure Interactive visual · bess.engineer
Voltage drop, in context.
The Grid-Scale BESS course covers voltage drop — and the rest of the system — from the ground up, the way it actually gets deployed.