Course cover: a data-center campus at dusk seen from above, with rows of battery containers and a substation beside the data halls, titled Powering AI Data Centers, From Backup Power to Grid Support

Powering AI Data Centers: BESS, UPS & Grid Integration

Self-paced video course · In production · by the end of November 2026 · 7 modules · 20 lectures · 3h planned

For engineers entering the data-center market, BESS and UPS product and sales teams, developers, consultants and procurement specialists. Assumes basic familiarity with electrical power, energy and AC/DC systems; no data-center design experience. Who it's for 

Delivered complete by the end of November 2026. Full refund any time until release, then within 7 days of release, provided less than half the course has been completed. How the refund works → In the EU, the EEA and the UK, you can withdraw within 14 days of buying for a full refund, whatever you have watched: see Refunds.

Buying for a team? Contact us

Double conversion, and an AI load swing.

The double-conversion scheme, one of the four site BESS integration schemes the course compares, and a simulation of an AI load at the point of interconnection, without and with an AI UPS.

Double conversion
Double-conversion scheme Grid, then the POI, then PCS 2, grid-following, a rectifier from AC to DC; the DC link with the battery; then PCS 1, grid-forming, an inverter from DC to AC; then the data center. Bypass: open in normal operation, used for maintenance or faults. Grid-following in, grid-forming out; PCS rating: 2× load. GRID-FOLLOWING IN GRID-FORMING OUT PCS RATING: 2× LOAD Grid POI Battery DC link Data center PCS 2 grid-following rectifier · AC → DC PCS 1 grid-forming inverter · DC → AC Bypass: open in normal operation, used for maintenance or faults Double-conversion scheme Grid, then the POI, then PCS 2, grid-following, a rectifier from AC to DC; the DC link with the battery; then PCS 1, grid-forming, an inverter from DC to AC; then the data center. Bypass: open in normal operation, used for maintenance or faults. Grid-following in, grid-forming out; PCS rating: 2× load. GRID-FOLLOWING IN GRID-FORMING OUT PCS RATING: 2× LOAD Grid POI Battery DC link Data center PCS 2 grid-following rectifier · AC → DC PCS 1 grid-forming inverter · DC → AC Bypass: open in normal operation, used for maintenance or faults Double-conversion scheme Grid, then the POI, then PCS 2, grid-following, a rectifier from AC to DC; the DC link with the battery; then PCS 1, grid-forming, an inverter from DC to AC; then the data center. Bypass: open in normal operation, used for maintenance or faults. Grid-following in, grid-forming out; PCS rating: 2× load. GRID-FOLLOWING IN GRID-FORMING OUT PCS RATING: 2× LOAD Grid POI PCS 2 grid-following rectifier · AC → DC Battery DC link PCS 1 grid-forming inverter · DC → AC Data center Bypass: open in normal operation, used for maintenance or faults
AI UPS, simulated
AI UPS simulation Simulation over 7 seconds, without and with an AI UPS. Active power at the POI, MW: POI swing: 2.25 MW → ≈ 0.6 MW. Voltage at the inverter terminals, pu: Stays within 2.6%. Without AI UPS With AI UPS Simulation 0 1 2 3 0.98 0.99 1.00 1.01 1.02 0 s1234567 Active power at the POI, MW POI swing: 2.25 MW → ≈ 0.6 MW Voltage at the inverter terminals, pu Stays within 2.6% 2.6% AI UPS simulation Simulation over 7 seconds, without and with an AI UPS. Active power at the POI, MW: POI swing: 2.25 MW → ≈ 0.6 MW. Voltage at the inverter terminals, pu: Stays within 2.6%. Without AI UPS With AI UPS Simulation 0 1 2 3 0.98 0.99 1.00 1.01 1.02 0 s1234567 Active power at the POI, MW POI swing: 2.25 MW → ≈ 0.6 MW Voltage at the inverter terminals, pu Stays within 2.6% 2.6%

Instructor: Sergey Syrvachev Director of Product Engineering, HyperStrong

From backup power to grid support.

AI data centers need continuous power, access to capacity and infrastructure that can handle rapid changes in computing demand. Battery energy storage systems (BESS) can help, but their value depends on where they connect, how they are controlled and which loads they protect. This course gives you an overview of the power challenges data centers face, and a practical framework for comparing those choices.

In 3h of lectures, you will follow the power path from the utility connection to the GPU rack. You will learn how switchgear, transformers, uninterruptible power supplies (UPS), generators and cooling systems work together, and why IT load, total facility load and protected load are different quantities. You will also see how rising rack density and the search for earlier power availability are changing project decisions.

The course explains reliability through both equipment and behavior. You will distinguish redundant capacity from independent power paths, examine N, N+1, 2N and distributed redundancy, and follow a utility outage through battery support, generator pickup and recovery. A concise standards overview separates Uptime Tier classifications from TIA-942 infrastructure requirements and ASHRAE thermal guidance.

Next, you will examine synchronized AI load swings and their effects on the grid and on-site generation, and weigh the options: software controls, rack capacitors, battery backup units, UPS-based smoothing and site BESS. Grid-following and grid-forming controls are introduced through their functions and operating limits.

The commercial discussion connects technical choices with time to power, capital cost, operating duty and potential grid-service value. The final architecture section introduces 800 VDC, sidecar power racks and solid-state transformers as the next steps in how these solutions are developing.

Level

Practical foundation with intermediate worked examples.

A knowledge check in every lecture

Each of the 20 lectures ends with a knowledge check, listed under it below. The last lecture returns to the 120 MW protected-load example in six case-based questions, revealing the reasoning after each.

20 lectures, from the power problem to 800 VDC.

The course follows the power problem, equipment and reliability requirements before comparing BESS functions, integration choices and emerging DC architectures.

20 lectures · 3h planned

    • 1 Why AI changes the data-center power problem 6 min

      Knowledge check: Identify which problem is about capacity, which is about continuity and which is about rapid changes in demand.

    • 2 Time to power, flexible connections and on-site generation 8 min

      Knowledge check: Explain who supplies the gap when a connection permits less import than the facility needs.

    • 3 Follow the power from the grid to the GPU 8 min

      Knowledge check: Mark the IT-load boundary and the wider protected-load boundary on one power path.

    • 4 UPS batteries and generators through an outage 13 min

      Knowledge check: Narrate utility loss, battery support, generator pickup and return to normal operation.

    • 5 Cooling, PUE and the load that must stay alive 8 min

      Knowledge check: Explain why backup sizing cannot use IT MW alone or assume every cooling load has identical ride-through needs.

    • 6 Uptime, TIA-942, ASHRAE and what Tier ratings mean 8 min

      Knowledge check: Explain why N+1 equipment and a quoted availability percentage do not establish Tier III.

    • 7 Redundant capacity, independent paths and outage behavior 10 min

      Knowledge check: Take one component out of service and decide whether the load still has sufficient capacity and a working path.

    • 8 AI load swings and their impact on the grid 10 min

      Knowledge check: Identify the relevant disturbance and measurement boundary for three load-change examples.

    • 9 Grid requirements and four ways to manage AI swings 7 min

      Knowledge check: Choose which layer should address a fast rack transient and which layer manages the site import profile.

    • 10 PCS control, smoothing, ride-through and generator bridging 10 min

      Knowledge check: Explain what evidence is missing when a proposal says only that its PCS is grid-forming.

    • 11 Backup reserves, grid services and the commercial case 9 min

      Knowledge check: Determine which services remain possible when SOC is near the backup floor or upper limit.

    • 12 Battery technology, safety and warranted operating duty 5 min

      Knowledge check: Identify the duty and safety evidence to request before accepting a vendor’s battery-life claim.

    • 13 Power modules and distributed redundancy 9 min

      Knowledge check: Under the illustrated balanced dual-feed mapping, check the 6.6 MW load after one 2.4 MW module is unavailable, then explain why losing two modules is different.

    • 14 Compare four site BESS integration schemes 10 min

      Knowledge check: Shortlist a scheme for a grid-connected site and an islanded site, stating the assumptions that could change each choice.

    • 15 Worked example from protected load to MW, MWh and MVA 15 min

      Knowledge check: Explain why 48.8 MWh and 250 MWh answer different sizing constraints, and why 123.6 MWh is not always available for dispatch.

    • 16 UPS smoothing, rack capacitors and battery backup units 11 min

      Knowledge check: Choose the layer that fits the required timescale and identify the loads it actually protects.

    • 17 From supplier proposal to acceptance testing 8 min

      Knowledge check: Turn one generic supplier promise into a test with an operating condition, measurement boundary and pass criterion.

    • 18 Why 800 VDC changes the power architecture 7 min

      Knowledge check: Calculate the ideal DC current at 1 MW and 800 V, then state one practical limitation not captured by that calculation.

    • 19 SSTs, DC protection and storage on the DC bus 8 min

      Knowledge check: Identify the architecture, grounding and protection questions that must be resolved before an 800 VDC concept becomes a project.

    • 20 Final case review and knowledge check 10 min

      Knowledge check: Complete the six-question case check: four minutes of guided pauses and six minutes of answer explanation.

Lengths are the course plan’s, in minutes.

All 20 lectures and their knowledge checks are planned in full. Pre-order this course

What you will be able to do.

  1. Trace a grid-to-rack power path and distinguish IT load, facility load and the load that must remain protected.

  2. Explain the separate roles of UPS systems, generators, PCS, site BESS, rack capacitors and battery backup units.

  3. Distinguish redundancy counts from independent supply paths, maintenance capability and Tier certification.

  4. Interpret AI load swings and identify the power, energy and converter-current limits.

  5. Compare power modules, site BESS schemes, UPS smoothing and rack buffering for a stated requirement.

  6. Check backup reserves and charging headroom before assigning spare capacity to smoothing or grid services.

  7. Explain how 800 VDC changes power conversion, storage placement and protection questions.

  8. Identify vendor information and know which major vendors supply the power equipment.

The final case, in six questions.

Lecture 20 connects sizing, reserve, supply paths, control limits, commercial value and acceptance evidence. A longer written recommendation is optional practice.

  1. Why does the 120 MW case produce both a 48.8 MWh energy bound and a 250 MWh power screen?

  2. At 80% SOC in the illustrative 10–90% window, what reserve and charging room remain?

  3. Why do spare modules alone not prove concurrent maintainability?

  4. Does a grid-forming PCS establish uninterrupted service through every grid event?

  5. Which benefits can be credited to the BESS commercial case?

  6. What would turn a backup-duration claim into an assessable acceptance requirement?

Who it is for.

  • Electrical and energy-storage engineers entering the data-center market.

  • BESS, UPS and power-equipment product managers and technical sales teams.

  • Data-center developers, project managers and commercial teams assessing power options.

  • Energy consultants and procurement specialists reviewing supplier proposals.

Built for engineers, project developers, product managers, technical sales teams and commercial professionals, the course combines system explanations and decision exercises. You will finish better prepared to compare proposals, identify missing assumptions and discuss requirements with customers, utilities and equipment suppliers.

Before you begin

Basic familiarity with electrical power, energy and AC/DC systems is helpful. No data-center design experience is required. Short worked examples use arithmetic and a square root; a calculator is sufficient. Acronyms are introduced as they appear.

Related deep dives: BESS Engineering Foundations for the electrical model under the sizing — DC and AC fundamentals, P-⁠Q capability and MVA headroom — and How a Battery Gets Paid for the revenue stack behind grid services. The Grid-Scale Complete Guide supplies the wider system picture if you are new to BESS. Free reading: Why Megawatts Are Not Enough: Sizing a BESS for AI Load Ramps.

Buying details

  • Is it available now?

    This deep dive is in production — pre-order it now, refundable in full until release and for 7 days after. Meanwhile the Grid-Scale BESS Complete Guide covers the batteries, enclosures, PCS and controls this course builds on.

    Your course space opens at purchase in your training.bess.courses classroom — the finished course lands there complete, not as a drip of sections, by the end of November 2026. Full refund any time until release, then within 7 days of release, provided less than half the course has been completed.

  • How long does it take?

    3h planned · 7 modules · 20 lectures

  • Is there a certificate?

    Certificate: decided and announced at release. BESS course certificates.

  • Where do I buy it?

    This is a separate specialist course, not a section of the Complete Guide the same instructor sells on Udemy. What differs

    Secure checkout by Stripe — card, Apple Pay and Google Pay. The lines under each price say whether tax is included and, where we can estimate it, about what Stripe will show in your own currency.

  • Which email do I use?

    One-time purchase with lifetime access — no subscription. Your access link arrives by email within minutes of payment and opens your course space. The access link goes to your payment’s email (with a wallet, that may be the wallet’s). You can change it on the page after payment.

    Already bought it? Open your classroom 

  • Can my company pay?

    Company paying? We can invoice your employer — email sergey@bess.courses with the course and your company name. After your company's paperwork, the invoice arrives by email within 24 hours, due in 30 days; access starts as soon as it is sent.

  • Students and early-career engineers?

    Student or early-career engineer? The Complete Guide is free for you, and every specialist course and the bundle are 50% off. The student discount does not combine with any other discount, early bird included. How to claim it 

  • Is it in the Professional bundle?

    Yes. The Professional bundle includes all six BESS.courses courses.

Buying for a team? Contact us

Back to the price